Last Updated | 03/18/2023 05:08 AM |
Project Title | Cedar Road Improvements, Balsam Road to Lowes Creek Road WisDOT 2022-2023 LRIP TRI-S Project |
Physical Address | View project details and contacts |
City, State (County) | Eau Claire, WI 54701 (Eau Claire County) |
Category(s) | Heavy and Highway, Sewer and Water |
Sub-Category(s) | Maintenance, Paving/Reconstruction, Shoreline/Erosion/Drainage, Site Development, Water Lines |
Contracting Method | Competitive Bids |
Project Status | Results, Construction start expected April 2023 |
Bids Due | View project details and contacts |
Estimated Value | $676,798 [brand] Estimate |
Plans Available from | Civil Engineer |
Owner | View project details and contacts |
Architect | View project details and contacts |
Description | Clearing and grubbing, removals, sawcut, asphalt pavement pulverizing and relay, excavation, storm sewer culverts, driveways, crushed aggregate base and shoulders, hot mix asphalt pavement, pavement marking, erosion control, traffic control, topsoil/turf/erosion mat/grasses. The work, in general, will include the approximate quantities and items listed below: Clearing and Grubbing 0.70 acres Sawcut 300 lf Excavation 2,550 cy Borrow Excavation 500 cy Culvert Storm Sewer, 12" - 36" HDPE 618 lf Culvert Storm Sewer, 71" x 47" CMP 56 lf Storm Inlet, Type III 1 ea Asphalt Pavement Pulverizing 14,000 sy Crushed Aggregate Base 3,550 cy Crushed Aggregate Base, Shoulders 9,685 lf Concrete Curb and Gutter, 30" Barrier 100 lf Hot Mix Asphalt Pavement, 2" Binder 17,540 sy Hot Mix Asphalt Pavement 2" Surface 17,540 sy Hot Mix Asphalt Pavement, Driveways 430 sy Pavement Marking Lines, 4" Epoxy 10,360 lf Traffic Control 1 ls Topsoil, Turf, Grasses, and Erosion Mat 13,450 sy Riprap, Medium 80 sy This project is part of a WisDOT Local Road Improvement Program (LRIP) TRI-S project, which consists of roadway improvements of existing road including clearing and grubbing, asphalt pavement pulverizing and relay, widening, excavation, storm sewer culverts, driveways, crushed aggregate base, hot mix asphalt pavement, and restoration. The Work will be substantially complete on or before September 1, 2023; final completion on or before October 6, 2023. Location: Cedar Road, Town of Pleasant Valley, Eau Claire County, Wisconsin. The Work includes: a. Excavation b. Trenching, backfilling and compacting c. Asphalt pavement pulverizing d. Clearing and grubbing e. Erosion control f. Traffic control g. Storm sewer culverts h. Sawcut i. Riprap j. Crushed aggregate base k. Hot mix asphalt pavement l. Concrete curb and gutter m. Pavement markings n. Topsoil, turf, grasses, erosion mat Interpretations or clarifications considered necessary by Engineer in response to such questions will be issued by Addenda delivered to all registered plan holders. Questions received less than five days prior to the date for opening of Bids may not be answered. Russ Kiviniemi, 715-235-9081 or russ.kiviniemi@cedarcorp.com. |
||||||||||
Details |
|
||||||||||
Bidder's List | View project details and contacts | ||||||||||
Prospective Bidders | View project details and contacts | ||||||||||
Project Documents |
Engineered Spec Sheet Architectural Plans Other Documents |